Saturday, October 9, 2010

International Technical Officials Shifted to Hotels: Facing Commuting Problems

When the organizing committee (OC) decided to move its international technical officials (ITO) from Vasant Kunj to different hotels in the NCR, it wouldn’t have thought its decision would come to haunt it later. Complaints from delegates about long wait for transport, combined with a long commute, have now forced the OC to re look at its transportation plans.

Said an official, ‘‘Delegates have been complaining about the wait for transport to the venues and back to hotels, especially since most have schedules starting really early in the day.’’ Sources say the logistics behind getting all the delegates to the venue and back to various hotels in the city is the root cause of the problem. With ITOs staying in 12 different hotels in Delhi and NCR, including Gurgaon and Faridabad, sources say picking up the ITOs and dropping them back is a long process every day. Interestingly, the delegates from a particular sport are not necessarily staying together, making it impossible for the vehicle to be confined to a single hotel.

Compounding the problem is the acute lack of drivers that the OC has been facing. Of the 2,200 that were to be provided to the OC by Tata motors, many left the OC hanging, disappearing midway through the first week itself. Now, the OC has hired over 500 drivers from schools in the city, hoping the drivers familiarity with the city will help them get the delegates faster from point A to B. Admitted Jiji Thomson, special DG, OC and in charge of transport, ‘‘The situation has improved tremendously from what it was last week. It should get even better over the next few days.’’ On Friday, Commonwealth Games Federation (CGF) CEO, Mike Hooper, said no complaints had been received about transportation, hoping that the problem had been resolved.

Meanwhile, sources say that the lack of drivers has been a source of much aggravation for many delegates till date. The ITOs consisting of judges and other technical delegates were to be provided individual cars as part of the Games protocol. These were to be with them through the day, so that commuting between events and venues is easy. However, with few drivers around, many had to share the transport, leading them to wait for the cars as it ferried other delegates. Added the source, ‘‘Though monitoring of the cars is constant through GPS, there were instances when delegates had to wait for half to one hour for their transport.’’

On Friday though, the OC finally put 600 cars specifically for shared transport after new drivers were taken in, with another 300 being added to the T1 (individual) fleet.

Tuesday, September 21, 2010

Blockages Leading to Water Accumulating at IG velodrome: Drainage a Big Problem

A couple of days left to athletes arriving in India for the Commonwealth Games 2010 and venues in the city continue to face problems. Sources working at the Indira Gandhi Velodrome say the drainage system at the venue has sprung blockages, leading to water accumulating within the premises.

Said a senior official, ‘‘The drainage system, which is supposedly state-of-the-art, however hasn’t managed to tackle the rainwater. The rain over the past few days has been very strong, which has led to the blocks in the drainage system.’’ The situation is so bad that water can be found to be lying in large quantities around the premises, as well as leading to seepage, add officials working in the site. The situation is especially precarious in the roof, where the accumulating water could well lead to leaks, added the officials. ‘‘Since its a closed stadium, the rainwater needs to be taken out through the pipes along the roof. However, since the drainage system is not working at optimum, the water flows out of the pipes and leads to leaks. A physical outlet had to be made to take out the excess water,’’ said the official.

Officials in the CPWD deny the allegations. Said BK Chugh, director general (works) of the CPWD, ‘‘There are no problems with the drainage in the Indira Gandhi velodrome. Its one of the most sophisticated venues we have constructed, with the latest technology.’’ Chugh claimed that the water accumulation was a temporary feature because of the rains and not because of a faulty drainage system. ‘‘The last time there was a problem was a fortnight ago, which was resolved. We have received no complaint from the Velodrome thereafter, and have been conducting daily checks,’’ added Chugh.

Media & Broadcast Centre with the Capacity of 2000 Journalists open

Dismissing travel advisories issued by Commonwealth countries, Organizing Committee chairman Suresh Kalmadi on Monday said no country had expressed concern or threatened to pull out of the Commonwealth Games after the Jama Masjid shooting incident.

He said all steps had been taken to ensure safety of athletes and delegates were satisfied with the arrangements made by India. ‘‘We are monitoring the situation on a day to day basis,’’ said Kalmadi while inaugurating the main press centre of the Games at Pragati Maidan. He was accompanied by I&B minister Ambika Soni.

Spread over 6,700sqm, the media centre will cater to about 2,000 journalists including 800 from overseas. It is expected to function 24 hours from October 1-15. There will be free internet access and wi-fi.

The International Broadcast Centre also situated at Pragati Maidan has begun operations with broadcasters setting up operations there. IBC is equipped with technical resources, including broadcast information offices, satellite dish farm and telecommunication operations.

Uncompressed audio and video feed from 38 cameras produced by the host broadcaster from all venues through optical fibre connection will be customised by rights holding broadcasters and transmitted through satellite uplinking service and international fiber service.

‘‘I have not got a single call from any Commonwealth country expressing apprehensions about security (of the athletes after Sunday’s firing). This (firing) was not a Games-related incident. It happened in Jama Masjid and the police are looking into it. It’s not a major incident. As of today, all 71 Commonwealth countries are coming for the Games,’’ he added.

Asked about terror advisories issued by various countries, Kalmadi said their respective Commonwealth Games associations have committed to participating in the multi-sport event. ‘‘Many countries have issued travel advisories earlier also. Australia had earlier issued an advisory but its Commonwealth Games chief Perry Crosswhite said its athletes are coming. So what is important is that the Commonwealth Games bodies of the respective countries have committed to participation in the Games,’’ the OC chief added.

Monday, August 30, 2010

Shivaji Stadium to miss games deadline

After the Central Vista, it seems to be the turn of Shivaji Stadium to miss the Commonwealth Games 2010 deadline. The stadium, which is being built by New Delhi Municipal Council (NDMC), was to be part of the list of practice venues for athletes who are expected to start arriving from September 23. However, organizing committee (OC) officials say the facility is not even near completion. ‘‘As of now, we are not taking a call on Shivaji Stadium. We have already lined up other venues in case the stadium is not completed on time,’’ admitted Lalit Bhanot, secretary general, OC.

Earlier last month, Central Vista where the finals of the archery event were to take place was taken off the list of venues for Delhi Games 2010. Reason: late start of work. In fact, preparations for the event, which involved setting up temporary structures, had not even started. The finals were then shifted to Yamuna Sports Complex the competition venue for archery.

In case of Shivaji Stadium, NDMC claims the stadium is being rebuilt for legacy purposes. However, with only a part of the stadium expected to be handed over to the OC, the fact is that the stadium was to be the training venue for hockey. This was revealed by the ministry of youth affairs and sports, which has the stadium listed on its training venue schedule.

Anand Tiwari, NDMC spokesperson, claimed the civic agency had only been asked to hand over parts of the stadium to OC. Said Tiwari, ‘‘A major portion of the stadium building is for legacy purposes. Only the field of play, ground floor and the technology room is to be handed over to the OC by mid-September and we are working on it.’’

OC officials claim even if the stadium is not complete on time, it will use the premises of other competition venues for training purposes. The stadium, which had been intended for hockey practice and as a swimming arena, will now be replaced by Major Dhyan Chand Stadium and SP Mukherjee Swimming Pool Complex. With not even the structure of Shivaji stadium near completion, it seems the stadium will not be ready for practice sessions. Said a senior NDMC official, ‘‘There is a lot of work to be completed, and the field of play is yet to be ready.’’

Incidentally, Shivaji Stadium is not the only training venue to be lagging behind. Both Delhi Development Authority (DDA) training venues Yamuna Sports Complex and Siri Fort complex are still to be completed.

Sunday, August 1, 2010

EXPOSED: Main Venues are not Ready

From the outside, Karni Singh Shooting Range one of the venues of Commonwealth Games looks like a fortress complete with very high stone walls, recently extended with more stones, and glistening barbed wire. Inside, it’s a chaotic construction site with mounds of earth and paving stones dotting the area. The armed CISF men though give away the fact that this is not just any construction site but the venue for a world class event that is due to start in less than 70 days.

Given the present state of complete unprepared ness with even the entry points being kuccha tracks, it is difficult to imagine that this venue had in February hosted a test event. Just after one enters from Gate No. 2, having braved a long grilling session by the CISF who make it clear that the area is out of bounds, specifically for the media there is a pile of bricks and a splotch of blue paint, signs that the venue is still many days away from completion.

No wonder that Sports Authority of India, whose property the range is, chose to cordon off or block from sight most of the ground leading to the shooting ranges during the test event.

Both sides of the concrete paths leading to the four main ranges are completely dug up with parts of cables and pipes sticking out here and there. Intermittently, there are massive holes in the ground, waiting for the trees that will be planted for landscaping and beautification purposes.

When you enter from Gate No. 3, the scene inside is even worse with guards sitting on heaps of earth chewing tobacco.

Obviously, security is not an issue when workers get hired here. A labourer working at the site claimed he had been approached by the local thekedar and had been working at Karni Singh for the past month. ‘‘They picked me from the main road a month ago, and I have been working here ever since,’’ he said. According to him, there was a lot left to be done at the venue. It will take at least one month to clear the area of all the rubble and plant the trees.

The only part of the scene which looks complete and therefore strikes a discordant note with the rest of the landscape is the array of green boards with Shera on them. Earth movers move in and out of the complex while paving stones are stacked here and there, waiting for the premises to reach a stage where they could be used.

Work is also going on at a furious pace along the approach road to the range. Bulldozers can be seen planting trees along the Suraj Kund road, a forest area. Ironically, local MCD workers say there isn’t much space left to plant more trees.

Says a worker, Nau Bahar, ‘‘I have orders to plant 250 trees on this road but as you can see there is no space for that kind of growth.’’ So, old trees will have to make way for new ones.

Outside the range, the long and winding road to Faridabad is a unique sight. Both sides have been paved to resemble a footpath but there is no variation of level. Why the paving then? The paving tiles are breaking down under the weight of the bulldozer which is assigned to dig up the ground to plant more unnecessary trees.

Some distance off, the parking which will house some 1,000-odd cars is still a green field. The supervisor sitting in the shade of a tree says work started a fortnight back and will be ready by August 15. One cannot help wonder how.

Sport Venues are Not Ready

It’s hard to believe that the Yamuna Sports Complex (YSC) in Vivek Vihar, the main competition venue for table tennis and archery, is ‘‘99% complete’’. Work is still going in the main stadium. Pipes lie along the corners perhaps a result of the repair work on the roof after the false ceiling collapsed on July 13 and tiles are strewn all over the places.

The Delhi Development Authority (DDA) however, maintains that the complex is ready to be handed over to the Organizing Committee (OC) on August 1.

That there’s a wide gap between the DDA’s claims and the ground reality can be easily ascertained as one walks down the complex. Security is tight members of the complex are the only ones allowed in for morning walks and even these are frisked to ensure they don’t have cameras. Entry of media is strictly banned. The extreme caution seems understandable when you see the huge amount of work that still needs to be completed at the complex. Ironically, the Yamuna Sports Complex was inaugurated way back in March by the urban development minister.

Insiders say the biggest obstacle in the preparation has been the installation of the roof over the main stadium. Designed according to international norms, the roof, material for which has been imported, has been posing an architectural puzzle to DDA engineers since the beginning. That the puzzle hasn’t been successfully solved was made apparent earlier in July, when accumulation of rainwater led to a large section of the false ceiling collapsing. Repair work is still underway, with engineers putting in a restructured system for pipes on the roof for proper drainage.

‘‘Earlier, the drainage pipes were laid in the middle. Now, these have been positioned along the sides. Drainage ducts in corners have also been factored in,’’ says an official at the site. Interestingly, the expensive wooden flooring, which has been installed as part of the FOP (field of play) has been left exposed precariously to weather the ongoing construction work.

Outside, the scene is no better. Like the other Commonwealth Games venues, landscaping seems a distant dream, with mounds of dug up earth and rubble all over the place.

The worst is the site for the swimming pool a training venue for athletes. DDA officials admit this will not be complete before mid-August. Metal pipes, parts of broken down walls, bricks and other malba litter the entry to the stadium. DDA’s plan to implement a proper pedestrian pathway seems ambitious at this point in time. Meanwhile, seepage can be seen along many areas of the complex, raising questions about the quality of the work here.

With little time left for OC to begin its overlay work, YSC may be the most difficult venue to start work from, admit sources. ‘‘A large part of the overlay work uses soft overlays, which will be completely destroyed if the sites don’t become ready fast,’’ says an OC official. DDA however, insists everything is on schedule. ‘‘The venue will be ready on time. We just need to complete the peripheral work,’’ says a senior DDA official. Actual picture is, of course, quite different.

IN THE MAKING

Venue for | Table tennis and archery

Cost Rs 25 crore

Seating capacity 3,500

Built over 4.8 hectares

The complex has been consistently missing deadlines. Previous deadlines were Dec ’09, March ’09 10 and June 2010. Now the work needs to be finished before August 2010

Portion of false ceiling at the table tennis stadium, which is being built according to a specialized international design, collapsed on July 13 after heavy rains

The collapse set back the work by a month DDA has spent Rs 79.20 crore on security at the sports complexes, evident at YSC which is heavily guarded YSC was originally built in 1989

Thursday, July 29, 2010

Yamuna Complex Project is Delayed

On a round to inspect Commonwealth Games projects of MCD and DDA in east Delhi, finance minister A K Walia on Wednesday expressed displeasure at the tardy pace of work at the Yamuna Sports Complex, where archery and table tennis events are scheduled to take place.

‘‘There is a lot of work pending and many efforts need to be put... The way the work is going on, I have doubts over timely completion (of some of the projects),’’ said Walia. A deadline of August 31 has been set by the city government for completing all the Games-related projects. Walia said that a few more extensions may be essential for the sports complex in particular, even though works on the roads and pavements are likely to be wrapped up with just some finishing touches remaining.

Walia reportedly pulled up officials but conceded that things have started looking up since the time the inspection by ministers started. ‘‘Things have improved since the last time we did inspection, but there is still a lot left to be done. And unless we really pull up our socks, some projects may miss the Games deadline causing huge embarrassment for the government. These visits by ministers have at least managed to infuse some sense of urgency in officials.’’

The minister expressed particular concern about the way construction rubbish still remains accumulated on several roads including in front of Akshardham Temple. He also pulled up officials for the broken pavements and ill-kept road near the temple which, because of its closeness to the Games Village, is likely to attract a lot of tourists during the Games.

Local Snack Makers Aiming for Games Catering

Some of Delhi’s more popular snack makers could turn out to be the new caterers for Commonwealth Games 2010.

Names like Haldiram, Bikanervala and Fast Trax are making the rounds at the OC office as the last date for the new RFPs (Request for proposals), issued last Saturday, draws near.

Sources claimed that feelers have already been sent by these companies to find out the requirements to compete for the request for proposals. Incidentally, the last date for the two RFPs one for packaged food packets for the workforce and one to cater at the VIP lounge is the end of this month.

Sources claimed that discussions between representatives of the companies and senior OC officials have been taking place over the past few days.

‘‘The interest expressed was for the packaged food RFP,’’ added the source. As part of the RFP, packed meals hour with the responsibility for packing and delivering the food resting with the caterer.

According to officials, a consortium could very well be formed to tackle the job.

With the organizing committee rejecting the proposal made by IRCTC for catering at all the venues, there is now pressure to choose the caterers before September 1, when the staff starts full-time work at the venues as well as at the trade fair grounds, where the media centre is located. According to sources, official functions there have been delayed due to the non-selection of a caterer.

Incidentally, the offer made by IRCTC had been for Rs 150 per plate, bringing the entire budget to a little over Rs 20 crore. Sources said that the OC was looking at more affordable prices.

The organizing committee has been struggling to find caterers for its venues for some time now.

The decision to go for packed meals for its workforce and food stalls in the VIP lounges has raised questions over food safety norms, with many pointing out the huge difference in quality that would become inevitable between the food provided at the Commonwealth Games Village by an international firm and what’s provided at the venues.

Things in Vein: Projects are not fully ready

The spanking new squash and badminton stadium, built at a cost of Rs 329 crore, is complete. Both match and practice courts have the field of play in place. While painting of the walls and rooms, last-minute work on the ceiling as well as touchup jobs like cleaning of windows and other glass enclosures remain, the Siri Fort stadium built by the Delhi Development Authority (DDA) at least looks like it is ready to host a sporting event.

Unfortunately, that’s pretty much all that can be said about this venue, which has been missing deadlines consistently. The landscape work which is sizeable as the stadium has been built on a large track of land (over 10 acres) is nowhere near completion.

Mounds of earth, to be used to construct the undulating green landscape in front of the stadium, lie around even as the temporary parking is still being constructed. An internal report puts the progress of work at 92%. Entry to the complex is hazardous since security bollards have just started being laid. Sources at the site admitted that the security measures, which are now being put in, will take some time to be completed. This includes the hi-tech scanners that will be set up so that screening of vehicles is a seamless process that is connected to centralized computers which will automatically check if the vehicle is safe.

Officials working on the system, being put in place by ECIL, say the entire process will take at least a month to be completed. The approach road, which DDA officials say will be built by the PWD, is only a mud track, which is being dug up to put in new cables. The road within the complex has been concretized, though the track along the Siri Fort Wall a heritage site looks in bad shape. The temporary parking behind the stadium, which was reportedly built over the existing green patch of the Siri Fort sports complex, has tiles lying around. Officials claimed these would be cleared ‘‘soon’’.

As you walk in, the impressive sight of the stadium is marred by the innumerable mounds of dug-up earth which have been left to be cleared by the landscaping department. DDA’s ambitious plan of covering the 10.91 acres of the complex with over 4,000 trees is not likely to be fulfilled. Sources admitted that plans of having seating arrangements along the front of the complex and the Siri Fort wall as well as food outlets have already been shelved. Saplings, which were both specially grown as well as bought by the land agency for a few lakh, can be seen rotting along the debris of the construction site. Officials said the stadium will be inaugurated ‘‘soon’’. ‘‘The basic structure is in place, we just need to finish the remaining. In fact, officials of the organizing committee have already started working from here,’’ said a senior DDA official. But with little being done on the large green tract of land within the complex and the slow progress of the security team, it looks like an uphill task.


VENUE FOR

Badminton and squash - TOTAL COST : - 329 Crore

VENUE OWNER

Delhi Development Authority Squash court built by Messrs ASB of Germany at a cost of
3 crore

Design of new stadium is Australian with even court seats being imported from there

The glass of the show court was specially imported from Germany

The show court can be dismantled and re-erected anywhere

SQUASH

10 courts; 1 match court; special wooden flooring

BADMINTON

3 practice courts and 5 match courts; special wooden flooring

Stadium has specialized aluminum acoustic ceiling

SEATING CAPACITY

Squash: 4,200
Badminton: 5,000

SEATING FOR PHYSICALLY CHALLENGED

30 in the squash stadium
50 in the badminton

TEMPORARY SEATING

2,928

PARKING AVAILABLE

Basement: 804 (not to be used during the Games);

Surface: 300 Temporary: 400

GREEN FEATURES:

Rainwater harvesting, affluent treatment plant, solar pre-heat system, re-use of treated water for horticulture, windows with double-insulated glazing

Saturday, July 24, 2010

Contractors Expressed their Inability of August Deadline

The two agencies working on the DDA flats at D6, Vasant Kunj walked out of the project earlier this month expressing their inability to meet the August deadline. The flats were to house 1,500 Indian and 650 foreign technical officials during the Delhi Games. The chief engineer of the site says only 604 of the 5,000-odd flats will be ‘‘definitely ready’’ by August-end while some more may be complete but he cannot give a figure to it. This despite the fact that in the June 29 GoM meeting, vice-chairman of DDA had said there was likely to be a shortfall of only 130 flats which are at a ‘‘very rudimentary stage’’. Chief engineer S R Solanki says DDA is looking at options to get the work done through work orders as there was no time to issue full-fledged tenders.

Solanki said: ‘‘M/s Brahmaputra and M/s A K Mehta were working on eight towers each. Earlier this month both wrote to us saying they cannot complete the work on time. So we are looking at other ways to get it done. Going by the present situation, 476 flats will be ready by the third week of August and another 128 will be ready by end-August. Some more may be complete but it is difficult to commit right now.’’

Interestingly, sources say when the work was awarded to the two agencies, the original plan was to incorporate 1% penalty for delays. However, the agencies managed to get a waiver on the ground that DDA’s lethargic way of functioning had already caused them to lose three months. DDA vice chairman had at the same meeting also informed the GoM that the authority was planning to get additional labor from non-CWG sites shifted to Vasant Kunj to speed up the pace of work which was to be monitored on a daily basis. The agencies walking out have put a spanner in the works. The GoM had talked about options of blacklisting defaulting contractors but DDA sources say that now the priority is to get work back on track rather than penalizing errant agencies.

Thursday, June 10, 2010

Athletes to be served by Village Caterer at Games venues

A week after an English daily Times of India reported that none of the firms except the one selected for the Commonwealth Games Village short listed for the catering tender has been given a letter of award or signed contract, OC spokesperson Lalit Bhanot said there wasn’t enough money to pay them and it must look at ‘‘reworking the scope of work”. The organizing committee (OC) top brass, including Chairperson Suresh Kalmadi, will be in London for a Commonwealth Games Federation meeting, delaying resolution of the impasse.

However, when the OC signed the contract with the consortium led by Delaware North for the Commonwealth Games Village earlier last month, the cost of the contract was over Rs 100 crore, say sources. ‘‘The Village contract itself is worth much more than the original estimate. Add the cost of the contracts for the sporting venues like Jawaharlal Nehru Stadium and National Stadium which comes to over Rs 70 crore, and the estimates go completely haywire,’’ said the sources.

They said the escalating costs prompted the OC to approach the Centre last week for a further loan of Rs 1,000 crore, a request that was turned down. Said a ministry official, ‘‘The government has already given a loan of Rs 1,620 crore to the OC for organizing the Games. The OC officials were told that they would now have to utilize their own resources to meet any cost escalation.’’

The result: sources say the OC is working to change the scope of the job that the firms would be handling. ‘‘The idea now is that instead of the venue caterer providing meals to athletes and officials, these would be packed at the Village itself. After all, the Village kitchen would be making 2,500 meals every hour anyway, so why have the venue caterer also provide meals to athletes,’’ said a source. That’s not all. There’s also talk of providing a pruned down menu at the venues, even at the opening and closing ceremonies.

The idea, however, has sent alarm bells ringing within the OC. Officials claim the talk of bringing down service levels could be a grave mistake as currently the standards maintained are of international level.

Thursday, February 4, 2010

250 sleek bus Q-shelters to come up near CWG venues

Aesthetic and sleek bus Q-shelters will soon dot the routes in and around Commonwealth Games venues with the Delhi Cabinet today approving construction of at least 250 such structures ahead of the mega sports event in October.

"DIMTS will take up construction of 250 modern bus Q-shelters on PPP basis on the same model as adopted in NDMC area and further take up construction of 800 more at the lowest rates received through open tenders," Chief Minister Sheila Dikshit told reporters after the Cabinet meeting here.

The total cost of construction is expected to be around Rs 96 crore, for which a request is being made to the Urban Development Ministry for sanctioning at least half the amount out of Delhi Development Fund.

Sunday, January 31, 2010

Karni Singh shooting venue for CWG Inaugurated

The second Commonwealth Games venue Dr Karni Singh Shooting Range was inaugurated on Sunday. The venue has been upgraded and renovated with an investment of Rs 150 crore in 13 months.

All the existing structures were demolished and new ranges with state-of-the-art technology were constructed. The earlier separate ranges for trap and skeet were converted into new composite ranges for trap and skeet with state-of-the-art scoring equipment. Before the Games in October, the Commonwealth Shooting Championship will be held at these ranges from February 17-28.

The renovated range spread over 72 acres in the backdrop of Adilabad Fort will have centrally air-conditioned indoor shooting range with 80 shooting points and a seating capacity of 500.

Saturday, January 30, 2010

Wrestling venue ready, shooting Venue by Next Sunday

It seems the nervous delays about Games venues is now a thing of the past. Five days after the first venue, Major Dhyan Chand National Stadium, was officially opened, Delhi chief minister Sheila Dikshit and organizing committee chairman Suresh Kalmadi on Friday inaugurated the Ludlow Castle wrestling training centre.

Next Sunday, Dr Karni Singh Shooting Range, the venue for shooting events, is scheduled to be officially completed. Two more stadia, Thyagraj and Chhatarsal would also be ready by March. PWD announced that it will also complete two infrastructure projects related to the Games every month.

Ludlow Castle wrestling training centre is the first venue built by Delhi government. ‘‘The wrestlers of the capital now have a great training facility. Once the Games are over, it will be very useful for children too,’’ Dikshit said.

Though the government had sanctioned Rs 20 crore, the project was completed at a cost of Rs 13 crore in 11 months. The venue was built after demolishing the badminton hall. The ground floor has various facilities such as restrooms, gym, cafeteria, physiotherapy centers, doping control centre, changing rooms, sauna bath and a medical centre. The first floor has a training hall, which can accommodate six wrestling mats at a time.

Last Sunday, the revamped Dhyan Chand Stadium was opened by Union sports minister M S Gill while both Dikshit and Kalmadi were reportedly not invited. However, on Friday, while both Dikshit and Kalmadi were present, Gill was missing. ‘‘This is a minor issue,’’ Dikshit told reporters.

Despite the progress, the CM said that it would be difficult to complete all projects related to the Commonwealth Games 2010 in the next eight months. ‘‘We need to work hard. There will be no excuse of rain or heat for delay in completing all projects. But I believe we will complete the work,’’ she said.

The CM also asked school students to be prepared to work as volunteers during the Games. Delhi government would provide 10,000 school guides for the inaugural function.

Praising Dikshit for her wholehearted support, Kalmadi claimed that the Games would be the best one so far. ‘‘It will be better than the Melbourne Games. We will try to bring the Olympics in 2020,’’ he added.

Thursday, January 21, 2010

UK is expected to send team of 1500 athletes and officials

Scotland Yard is likely to be involved in securing the Delhi Commonwealth Games to protect the British contingent. Nearly, 1,500 competitors and officials from the UK will participate in the Games, making it by far the largest presence from any country, said Ann Hogbin, chief executive of England Commonwealth Games Association (ECGA).

There will be 387 English athletes for the Games, Hogbin said, dismissing talk of the contingent opting out. ‘‘There is no uncertainty about England taking part and we are looking forward to doing so.’’

Last month, a section of the British press speculated that England may pull out on security concerns. Apart from Scotland Yard, ECGA has obtained advice from the British Foreign & Commonwealth Office and the Commonwealth Games Federation.

Jon Doig, chief executive of the Commonwealth Games Council for Scotland (CGCS), said security at the Delhi Games was an important issue and that CGCS had been receiving guidance from a range of people, including Scotland Yard. But he stressed his side’s preparations were on track and 200 Scottish sportspersons would be competing at the event. Chris Jenkins, chef de mission of a 170-member Wales squad, said: ‘‘We have raised security with the Met Police, Delhi Police and the CGFs consultants and have been reassured. It will be safe and spectacular Games.’’

Northern Ireland will be the fourth British contingent at Delhi. Beginning next month and up to May, British athletes will feature at test events at the various venues.

Tuesday, December 29, 2009

CPWD assures about the competition of the main venue before May 2010

The main venue for Commonwealth Games 2010, Jawaharlal Nehru Stadium, will be ready by May next year with the Central Public Works Department (CPWD) deciding to deploy more engineers and workers to complete the project before the revised deadline.

“I told the Rajya Sabha that the stadium will be ready in June. But I am going to increase the number of engineers and hope it will be ready by May,” sports minister MS Gill said after a meeting of the group of ministers (GoM).

Interestingly, Delhi chief Minister Sheila Dikshit had expressed concern over the delay in construction of venues, which are primarily the responsibility of the Sports Authority of India (SAI). “Everybody is happy with the preparations now. The work is progressing well,” Gill said. His assurance came after the Delhi CM had said she was “losing sleep” over the delay.

Similar sentiments were expressed by CPWD DG Bhishm Kumar Chug. “Yes, CPWD will make JLN stadium ready by May. Raw material from different countries has reached the venue and more engineers and workers have already been deployed to complete the work before the revised deadline of June,” Chug said. “In fact, in our internal schedule, it was to be completed by May,” he added.

Construction work at JLN stadium complex was initially supposed to be completed in February 2010 but the deadline was extended after a demand for a tunnel was made in October. The tunnel from the inside of the stadium was needed to facilitate the entry and exit of performing artistes at the opening and closing ceremonies.

Though it was initially opposed by Gill and CPWD on the ground that it would cause further delays, later on they agreed in order to make the opening ceremony a spectacular show. The GoM, which meets virtually every week to keep tabs on progress on various fronts, on Tuesday took stock of projects related to the October 3-14 Games.

Chairman of the organizing committee Suresh Kalmadi was also invited to the meeting to brief members on his recent meetings with CGF president Mike Fennell and on the overall progress of the Games projects.

Saturday, December 19, 2009

New Action Plan for 2010 CWG Venues

Commonwealth Games Federation president Mike Fennell on Saturday reacted to the delay in delivery of venues for the 2010 Games. ‘‘While I note improvement in operational areas, the organizing committee (OC) and its partners must maintain the momentum that they have now gained across all functional areas,’’ he stressed.

Fennell then expressed ‘‘great disappointment’’ over the findings of the CGF coordination commission on the delayed delivery of the venues, and in particular, at how the Jawaharlal Nehru Stadium, and the SP Mukherjee Swimming Complex were so far behind schedule.

‘‘We have continuously received assurances on the delivery timelines for these projects, and to now hear that there are further delays is distressing. These delays will have an impact upon the OC’s operational planning, particularly in relation to the conduct of test events and overlay installation,’’ Fennel added. ‘‘There can be no further delays,’’ he stressed, pointing out that he was pleased when sports minister M S Gill assured him on Saturday that the venues will not encounter any further delays.

Fennel next shifted gear to make statements that would be music to Kalmadi’s ears.’ With the backdrop of the coordination commission’s draft report and the positive progress made in operational planning, Mr Kalmadi and I have agreed today to an alternative approach to our ongoing interaction and monitoring work,’’ Fennel asserted.

‘‘In view of the current improved status, we have agreed it is now more appropriate for the CGF to provide additional on-going support to the OC through its existing Commonwealth Games Knowledge Management Programme,’’ Fennel added.

‘‘When I announced the formation of the committee just over two months ago, I noted that this group would monitor ‘progress against promise’. So now that will happen through our coordination commission and the ongoing work with OC of our CEO Micheal Hooper,’’ said Fennell.

Asked how there was this sudden sense of bonhomie between the CGF and the OC, Fennell was quick to say that the progress seen and the attitude towards the work at hand had definitely enhanced the confidence of the CGF in the OC and various stakeholders.

‘‘We can all have our different views but ultimately it’s job to work together to deliver the Games successfully,’’ he added.

A very nervous Suresh Kalmadi looked relieved at the announcement that the CGF won’t set up the Technical Review Committee. He admitted that the decision has brought a sigh of relief and harped on the fact how the CGF had witnessed improvement in the preparations.

ACTION PLAN
CGF decides against setting up of Technical Review Committee. Commonwealth Games Knowledge Management Programme to help

Assistance in three prime areas
Venue operations: Particularly the process associated with functional area integration at the time of Games
Volunteer programme: Particularly helping with the planning associated with training of 30, 0000 volunteers
Games readiness: Particularly successful demonstration of key capabilities and performance indicators

Friday, December 18, 2009

CPWD confident on timely completion of Venues

While completion of work at Jawaharlal Nehru Stadium will be slightly delayed from the March 2010 target for Commonwealth Games, Central Public Works Department (CPWD) the agency executing renovation and upgrade of stadiums is confident about meeting the new deadline for all other sporting venues.

Promising timely completion of Games-related works, CPWD director general Bhishm Kumar Chugh told ‘‘All the venues will be ready before March next year. The major thrust is on timely completion of work.’’

JLN Stadium will be ready by June next year as the decision to construct a tunnel from inside the stadium to facilitate entry and exit of performing artistes was only taken in October by the Group of Ministers (GoM) on request from the core team comprising Shyam Benegal, Prasoon Joshi and Bharat Bala which conceived the opening ceremony. ‘‘Work on the tunnel started on November 12,’’ said Chugh.

JLN Stadium work involves construction of a highly intricate structural system. CPWD has involved international experts from seven countries in the innovative and ambitious project. Apart from the main athletics venue, which will be ready by June, other venues like the weightlifting stadium and lawn bowl facility within the JLN Stadium complex will be complete by February 15, ahead of the March 2010 deadline.

With less than a year left for the mega event, the CPWD chief said Indira Gandhi Indoor Stadium will be ready by March 2010 and claimed that construction work was going on with renewed pace. At the IGI complex, the wrestling stadium will be ready by February 21. The cycling velodrome, for which work started only in January this year, will be ready in time along with the gymnastics stadium. ‘‘The IGI complex will be handed over by March,’’ said Chugh.

Though work started late due to a delay in the decision of number of lanes, the S P Mukherjee Swimming Stadium will be completed by March next year. ‘‘The daily target has been fixed now. Around 350 skilled workers are working in extended shifts to facilitate cable installation for the innovative cable net structure on which the roof will be placed,’’ he said.

Wednesday, December 16, 2009

Nehru Stadium Needs Some More time for Completion

As the first day of the review meeting of the coordination commission (CoCom) with the organizing committee kicked off on Monday, sources admitted that the OC has a tough job ahead.

From venue operationalization to procurement details, the CoCom would be looking at a much-improved preparation schedule to the Commonwealth Games 2010 — a task that, sources say, could get a jolt with the delay in operations of some of the key venues, specially Jawaharlal Nehru Stadium.

Said a senior official, ‘‘Though most of the venues are expected to be ready on schedule around March, the JN Stadium could get delayed beyond that.’’ This was also discussed at the annual general meeting held earlier this month, where it was revealed that JN Stadium may be handed over to the OC as late as May-June.

Incidentally, the stadium is the venue for not only the opening and closing ceremonies but is also the competitive venue for athletics and weightlifting.

Venue operationalization had been one of the major concerns of the Commonwealth Games Federation (CGF) at the general assembly meeting held in October this year. At that time, CGF chief Mike Fennell had raised questions about the OC’s preparedness on this front, apart from other areas of concern like the lack of international experts for various functional areas as well as procurement for the Games. OC officials, however, claimed the concerns raised at that time had all been addressed in the intervening two months.

While Kalmadi said ‘‘considerable progress’’ had been made in all areas since the last CoCom visit in May, he cited advances made in the functioning of the OC with a more relevant workforce as well as the appointment of experts in various key functional areas as right steps. ‘‘Finances are under control, with revenue from sales of TV rights having already exceeded expectations,’’ Kalmadi added.

That the OC is expecting positive feedback from the review meeting is apparent as secretary, ministry of sports, Sindhushree Khullar, candidly admitted that constructive advice was expected from the CoCom. ‘‘A lot of time has been spent in explaining things instead of getting on with the task of ensuring the Games are conducted well. The level of monitoring the progress of the Games has gone up. Your (CoCom) advice will help us get on with it,’’ said Khullar.

CoCom members were tightlipped about the meeting, with Mike Hooper, CGF representative in India refusing to comment on how the presentations went. The CoCom is expected to present its report to Fennell later this week.

Monday, December 7, 2009

Deadline for Hockey Venue: 15 December 2009

It’s a lesson in how to put the best foot forward. With intense interest being generated in the test events scheduled to be held in January 2010, the government seems to be working overtime to ensure that at least the first event goes off without a hitch. In a step in this direction, the organizing committee (OC) chairperson, Suresh Kalmadi has promised Major Dhyan Chand (MDC) stadium will be ‘‘complete’’ by December 15, 2009, ensuring that the test event is held at the venue as scheduled. Interestingly however, the events scheduled for some of the other competition venues like Thyagraj, have been postponed meanwhile.

Said Kalmadi recently on a site visit to MDC stadium, ‘‘The stadium will be ready before time, by December 15 itself. It will be one of the best hockey stadium in the world.’’ Incidentally, the stadium, which has been renovated at a cost of Rs 201.11 crore, is not only a competition venue but also a training venue with additional hockey pitches available at the Shivaji Stadium and Yamuna Sports Complex for the sportspersons. The stadium, which was originally set to be ready in September this year, is the first stadium which will host the test events, a kind of mock-Games for the city government. The 4-nation tournament is scheduled to be held from Janaury 13.

In contrast, the Thyagraj Stadium, which is the competition venue for Netball and where the test event was scheduled to be held in March, has been handed over a different timetable. Sources said the stadium, which is the only ‘green’ stadium in the city, will be ready only in February, when it is expected to be handed over to the OC. ‘‘The construction is going to finish by December 31, though the athletics track — Thyagraj is the training venue for athletics — will be ready in February,’’ added an official. ‘‘The test event, supposed to be held in March, has been tentatively set for July,’’ added an OC official.

OC secretary general Lalit Bhanot played down the rescheduling, claiming there had been no fixed schedule. ‘‘For Thyagraj, we had marked an invitation competition, which was not a fixed event. The event marked now will be the test event for the stadium,’’ insisted Bhanot, adding the stadium was otherwise ‘‘almost ready’’. Asked if other test events had been re-scheduled as well, Bhanot said both the hockey, shooting — in February in Karni Singh and CRPF ranges — as well as archery — in Yamuna Sports Complex — would take place as planned.

A Look At Games Plan

Major Dhyan Chand Stadium (hockey) DATE OF COMPLETION: 13-17
Jan Yamuna Sports Complex (archery) DATE OF COMPLETION:
7-14 March Thyagaraj Stadium (Netball) DATE OF COMPLETION: June-July (re-scheduled)