Wednesday, August 5, 2009

Commonwealth Games Boon For Overall Facelift of the City


Delhi is building an impressive infrastructure in the run-up to the Games but is struggling to address its power and water concerns. Times City concludes its Commonwealth stock-taking exercise with a final look at these two issues

This summer, as the mercury and consequently the demand for electricity soared, distribution companies (discoms) fell short by a massive margin in fulfilling the peak power requirements of Delhi, resulting in widespread protests. This has raised doubts over the power capital’s ability to host a power-packed event like the Commonwealth Games next year.

At a time when discoms are reluctant to buy expensive power to tide over the crisis, Delhi government is not taking chances. Against an anticipated power demand of about 4,000 MW in October next year, it has made arrangements for 5,600 MW. ‘‘We have entered into agreements for much more than the anticipated demand during the Games.

We have tie-ups with Damodar Valley Corporation (DVC) and the Centre. New power stations are coming up in Bawana, Jhajjar and Dadri. Though some units of the Bawana project are running into delays, these will be covered by the first deadline of the commissioning of the first unit in March next year,’’ said Delhi power secretary Rajender Kumar.

The government also promises two sources of power for all the stadiums so that if one fails, a back-up is always ready. ‘‘A third back-up is also in place for stadium-backed agency,’’ said Kumar. Besides these, the existing systems are being strengthened and the Centre has already clarified that the power from its share of unallocated quota, almost 4,000 MW, will be reserved for Delhi from October to December 2010.

Delhi’s crucial projects for the Commonwealth Games:

Aravali Super Thermal Power Project, Jhajjar

Capacity | 1,500 MW

Delhi’s share | 750 MW

Congress president Sonia Gandhi laid the foundation stone for this coal-based project in October last year. It will be a joint venture of NTPC, Delhi and Haryana governments. While NTPC will hold 51% stake, Delhi and Haryana will have 24.5% each.

The plant being constructed by Bharat Heavy Electricals Limited (BHEL) will have three units of 500 MW each. Delhi and Haryana will get 750MW each. The first unit of 500 MW is expected to be commissioned by June 2010 out of which Delhi will get 250 MW. The remaining two units are running into delay and while the second unit is expected to start by September-October, the third will only be commissioned by December 2010. ‘‘The delay is due to boiler supply and site works,’’ said an official.

But officials insisted the delay would not hinder their plans. ‘‘Up to 70% work on the first unit has been completed. PGCL will construct a dedicated line for transmitting power from Jhajjar to Mundka from where Delhi Transco take over,’’ said a power department official.

Dadri Thermal Power Station

Capacity | 980 MW

Delhi’s share | 900 MW


Delhi government signed a MoU with National Thermal Power Corporation (NTPC) for expansion of the Dadri Thermal Power Station with a commitment for 90% power share. The transmission line of this power station will also be laid by NTPC as the Electricity Act states that the responsibility lies with the generating company.

‘‘The first unit of this plant of 450 MW will be commissioned by November this year, which is actually ahead of schedule. The second unit of 500 MW is expected to be ready by February-March 2010,’’ said a senior official.

Pragati Phase III, Bawana

Capacity | 1,500 MW

Delhi’s share | 950 MW


This gas-based project is said to be running behind schedule but power department officials deny this. Awarded mega-power status certificate, the plant is entitled to get a waiver of Customs duty on imported plant and machinery. It will also get excise duty relief on indigenous plant and equipment, resulting in a saving of nearly Rs 200 crore on project cost.

It has six units four are gas based while two are steam based. ‘‘The first 250 MW unit is expected to be commissioned by March next year, while the other units would follow in May and August. But the plant has run into a three-month delay and the first unit will not be commissioned before June 2010. By the Games, four units will be commissioned,’’ said a source.

The project is critical for meeting the demand during the Games. The government has been projecting this project as the answer to Delhi’s power woes.

Damodar Valley Corporation

Capacity | 2,500 MW

Delhi’s share | 2,500 MW


It is expected to supply 2,300 MW by October 2010. But there has been some delay in the commissioning of units 7 and 8. According to Delhi government, power from DVC will flow to the city in phases and by 2012, Delhi will get up to 8,500 MW. Recently, Damodar Valley Corporation in Jharkhand had failed to deliver the promised power to Delhi on time. This has led to a massive shortage during peak summer months and long power cuts in the city.

What Delhi is doing to augment its supply?

Anticipated demand in Oct 2010 4,000 MW

Government’s arrangement for up to 6,000 MW

Crucial projects for 2010

  • Aravali super thermal project
  • Pragati phase III (Bawana)
  • Dadri Thermal power plant
  • Damodar Valley Corporation

What’s more?

4000 MW from the central unallocated quota two independent sources for all stadiums 108 MW from NDPL’s pilot power station, to be commissioned by June 2010 strengthening of transmission network and upgrading streetlights Agreements with Chamera (NHPC), Koldam HEP (NTPC)

Thursday, July 16, 2009

An Extra 80000 Mws to be Available within 18 Months

Keeping in mind, the huge power demand during Commonwealth Games in 2010 and as usual power deficit, government has taken up some very large projects for power generation, which will boost the power availability in coming months.

India's power availability will improve in the next 18 months as part of the 80,000 megawatts of capacity under construction comes on stream, Power Minister Sushilkumar Shinde said Wednesday.

India, which currently has an installed generation capacity of 149,391 megawatts, faces a peak hour deficit of 12% due to rising demand from industrial and household consumers.

The government plans to add 78,700 megawatts during the five years to March 2012 to meet rising demand.

"I am confident that we will be able to add at least 65,000 megawatts," Mr. Shinde told CNBC TV18 television channel, but he added that there could be delays due to adverse weather conditions and shortages of power generation equipment.

Mr. Shinde said he has already set a target to add 100,000 megawatts of capacity during the next five-year plan period that begins April 1, 2012.

India's planning panel sets targets for infrastructure development in power, roads, ports and other areas for five years, which are then pursued with funding from the government.

Saturday, July 11, 2009

Surplus Power for Delhi Before CWG Assures Power Minister

In present when mercury is soaring up new heights, citizens are fed up of humidity and frequent power cuts. With rains not coming just add up to worsen the situation. Hydroelectricity production has gone down considerably due to non availability of water in the storage dams.

Now power minister has assured to fight with this power crisis, let’s hope we see some good things in coming days.

Even as the capital faces an acute electricity crisis, power minister Sushilkumar Shinde on Friday assured the Rajya Sabha that Delhi will have surplus energy before the Commonwealth Games in October 2010.

Replying to a debate on the shortage of electricity in the country, Shinde said: “By October (next year), 5,000 MW to 6,000 MW of power will be available for the Commonwealth Games. Delhi will not be able to consume (that much) and will be in a position to sell the surplus,” he said.

Admitting that the Capital is facing an acute power shortage, Shinde said that at present the peak demand in the city is 4,400 MW. Giving details of power procurement for Delhi, Shinde said NTPC Dadri, Jhajjar, Koderma, Chandrapura and Durgapur, among others, will supply energy to the city. “We have some difficulty today, but this will be overcome,” he said, adding that by 2010, all villages would be able to get electricity six to eight hours a day.

The minister agreed there is a power shortage in India, but blamed the states for not generating enough in power.

Saturday, July 4, 2009

BSES to appeal against withdrawal of CISF security

BSES logoNearly everyone knows that a large part of unbilled electricity goes to electricity theft, not only in Delhi, this situation prevails all over India. These power robbers do not fear anyone, not even local police. For curbing power theft Central Industrial Security Force cover was provided to the distribution companies for performing their task efficiently. But now in a decision, government wants to pull back this cover. In such a situation how could we blame distribution companies, for not being able to stop this menace…..?

Calling it a setback, Power Company BSES Friday said it would appeal against the move to withdraw the paramilitary Central Industrial Security Force (CISF) security cover from power distribution companies.

We plan to appeal to the authorities concerned against the order (which came two days ago). Under the agreement, the services of the CISF had been provided to the distribution companies (discoms) for a five-year period. Its not fair for the service to be withdrawn after just a two-three year period, said a senior BSES official.

The official said that CISF’s withdrawal - a move BSES says it came to know of two days ago - is a violation of the Supreme Court order and is a huge setback to the success of public-private-partnerships in Delhi's power sector. CISF comes under the central home ministry.

In 2004, the Supreme Court had passed an order directing the state and union governments to provide the necessary security to the officials of discoms - NDPL (North Delhi Power Limited) and BSES - as required by them for anti-theft drives.

Each of the Delhi discoms had been provided a CISF company comprising 114 personnel to assist their enforcement teams in drives against power theft.

We were earlier told that the CISF cover is only being withdrawn on a temporary basis - till the elections are over. This decision has been a total shock to us. This will be a huge setback for us, in our drive against power theft.

“This decision may undo all the good work done by BSES on the power theft front in the last two to three years. Sans any protection now, we may not be able carry out raids in many of the power theft areas, the BSES official added.

When asked about the issue, a home ministry official said they are examining the matter.
We are examining the matter. We hope that we would arrive at a conclusion very soon, a home ministry official told .

Officials of the BSES on enforcement drives claim to have often faced physical attacks from mobs and anti-social elements during their anti-power theft drives. Discoms, including the BSES, had often requested Delhi Police to provide personnel but the already pressed force wasn’t available all the time.

The allotment of CISF to Delhi discoms gave the much needed impetus to discoms anti-power theft drives. Now they could go to areas, where they could not go earlier. With the CISF by their side, Delhi discoms were able to reduce AT & C losses to 20 percent (from a high of 63 percent in 2002), another BSES official claimed.

Under the agreement, each of the discoms had to bear an annual expense of around Rs.1.25 crore for getting the services of the CISF, in addition to providing them with accommodation and paying for their arms and ammunition

Friday, June 12, 2009

Dedicated Electricity Grid to Take Care of 2010 CWG

A dedicated electricity grid is to be set up for 2010 commonwealth games by BSES, one of the two private power distribution firms in the national capital. This project will cost around $8 million (INR 400 million). This electricity grid will exclusively serve the upcoming athletes village for the Commonwealth Games next year.

In an interview Lalit Jalan, the chief executive of BSES informed that the electricity grid will provide uninterrupted power supply to the 2010 Commonwealth Games, apart from continuous electricity at stadiums. This grid will be ready by the end of this year.

Keeping in mind the environmental measures, around 30 % area of the grid will be covered by trees. It will be a environment friendly and green grid, Jalan added, giving an update on the company, which is part of the Reliance Anil Dhirubhai Ambani Group (ADAG).

The grid will also have landscaping and deploy the latest energy conservation techniques, and will be located near the Akshardham temple across the Yamuna.

Counting on their achievements senior BSES officials said that in the seven years since distribution of electricity has been privatized in the national capital; the company has managed to cut the losses on account of theft and transmission to 20 percent from 60 percent.

“In the process, the Delhi government has been able to save Rs.13,729 crore (Rs.137.29 billion/$2.75 billion),” Jalan said.

Tuesday, June 9, 2009

Haryana advances power project commissioning for CWG

The Haryana government Saturday announced that the commissioning of the first phase of the state’s biggest power plant is being advanced to ensure power supply to the national capital much before the 2010 Commonwealth Games.

The first 500 MW unit of the prestigious 1,500-MW Indira Gandhi Super Thermal Power Project, being set up in Jhajjar district of Haryana, 200 km from Delhi, will now be commissioned in April 2010.

It will cater to the power requirements of the Commonwealth Games - the biggest sporting event in the country - to be held in October next year.

The schedule of implementation of the project was reviewed at a top level meeting by the union Power Secretary Harishankar Brahma and senior central and state officials of the power sector here.

Haryana Power Generation Corp managing director Sanjeev Kaushal said the construction work at the mega-status project was progressing as per schedule.

“Keeping in view the pace and progress of the construction activities, the commissioning target of the first 500 MW unit has been re-fixed for April 2010, well in time to cater to the power requirements of the Commonwealth Games to be held in Delhi,” Kaushal said.

Delhi will get 250 MW of power from the commissioned first unit of 500 MW.

Kaushal said the other two units of 500 MW each would be commissioned in October 2010 and January 2011.

The total estimated project cost is Rs.7,892 crore. An expenditure of Rs.2,543 crore has already been incurred on the project.

Thursday, April 16, 2009

RIL’s Gas Allocation will Boost up Power Situation in 2010 CWG

RIL’s Gas Allocation will Boost up Power Situation in 2010 CWGThe allocation of 18 million standard cubic metres of gas from the Reliance Industries Limited (RIL) KG Basin field for the power sector will come as a major boost to the efforts of the Government to enhance power production and would help many power-starved States and plants deal with the crisis more effectively during the summer season.

According to Power Ministry estimates, power plants having 14000 MW generation capacity had been producing only 7000 MW till now as they could not operate at their optimum capacity due to shortage of natural gas fuel. However, the major chunk of allocation of natural gas from the KG Basin will help them step up power generation and it is estimated that around 5000 MW of additional power would be available for distribution especially among Southern States during summer months.

The big beneficiaries would be the power plants in Andhra Pradesh which will be supplied 2.7 million standard cubic metres that include GMR’s Vemagiri, GVK’s Jegurupadu and Lanco’s Kondapalli unit. While other projects in Gujarat such as Essar, Gujarat Puguthan and Gujarat Industries Power will get 2.4 million standard cubic metres.

Official sources said RIL was expected to charge a marketing margin of 13.5-14 cents per mBtu over a base price of $4.2 and may agree to get paid in rupee terms as it did for fertilizer firms.
Not only this, important power projects like the upcoming Bawana power plant and additional power capacity expansion at Pragati Power plant in Delhi would get a boost ahead of the 2010 Commonwealth Games.

The beleaguered Dabhol power plant in Maharashtra is also likely to benefit from the latest decision of the Empowered Group of Ministers headed by External Affairs Minister Pranab Mukherjee. Around 4.5 to 5 million standard cubic metres of gas will be supplied to the power plants of National Thermal Power Corporation(NTPC).

Wednesday, April 1, 2009

Committing Uninterrupted Power for 2010 CWG Games: BHEL

Committing Uninterrupted Power for 2010 CWG Games: BHELBharat Heavy Electricals Limited’s project at Jhajjhar, Haryana, is a large 1,500 MW site (three units of 500 MW each).

It belongs to the Aravali Power Co., 51% owned by the National Thermal Power Corporation. (NTPC), 25% by the Haryana government. This project has been fast-tracked since it is expected to start supplying electricity in time for the 2010 Commonwealth Games.

Against planned execution of 21% of the project, BHEL has executed 13% due to delays in other parts of the project. Despite this, however, the company is confident of completing its part on time.

While the project has been placed on a fast track some challenges remain due to possible delay on others’ part. The areas of concern are obtaining canal water, the ash handling plant and a railway feeder line for coal supplies.

Judging by the site area, it can easily accommodate 2x500 MW units, which was also confirmed during our visit. When this happens, orders for boilers and steam turbines would most likely be placed with BHEL.

Monday, December 29, 2008

Sports Minister wants timely help for CWG athletes

2010 commonwealth gamesSports Minister MS Gill has asked the national federations to quickly settle contracts with coaches and ensure timely availability of sports and support equipment for the benefit of athletes undergoing training for the 2010 Commonwealth Games.

The directions were given after a review meeting of the progress of the 'Scheme for Preparation of Teams for Commonwealth Games' and and identification of steps required to further improve the working of this Scheme.

On the basis of feedback received during the meeting, which was attended by office bearers of different federations, officers of Sports Authority of India and Indian Olympic Association, several steps were identified to make the Scheme work more efficiently.

"The Sports Minister has given direction for ensuring that sports and support equipment and consumables are made available in time, contracts with coaches are settled expeditiously, progress of the Scheme be monitored closely and kits to sports persons coming to camps be given without any delay," a release from the Ministry said on Wednesday.

"It was also decided to make available training facilities at non-SAI venues in certain locations like Chennai for Swimming, Hyderabad for Badminton, Pune for Tennis and Shooting etc," it said.

Under the Scheme, which would cost the Government Rs 678 crores, the selection process for identifying about 1300 elite players, in 17 disciplines, 250 coaches (both Indian and foreign), and about 80 supporting personnel (physiotherapists, psychologist, masseurs etc) has been completed.

These elite players will be fully funded by Government, for intensive training of 305 days, in a year, both within, and outside the country. They will also be provided state of art, equipments, training and greater exposure in domestic and international tournaments.

The players will be assessed at regular intervals, through pre-decided monitorable parameters, till their final selection for Commonwealth Games.

The coaching camps for the selected players have commenced at the various centers of Sports Authority of India.

Wednesday, May 7, 2008

Preparations and Plans for Power Acquirements and Arrangements

power arrangement plans

National Thermal Power Corporation, Damodar Valley Corporation, Dadri power plant of NTPC, Jhajhar, Haryana plant and the Pragati power plant will start supplying around 4,240 MW of power to the city in the next couple of years.

The government is initiating certain corrective measures to maintain streamline power supply.

The government has plans to get 1,800 MW from local sources in addition to the existing installed power generation capacity of 932 MW.

The transmission and distribution loss is also a most important factor that has to be effectively addressed ,as it is the main cause of power loss. It was whopping high of around 49 percent in 2007-2008 whereas the National figure was of 30-31 percent. So this factor must be taken into account seriously otherwise all other measures will become less effective.

The government is also planning to add couple of projects for capacity addition in the coming 11th Five Year Plan period (2007-12) . At the moment, the city stands to get 750 MW from the upcoming power plant at Jhajhar in Haryana,which is expected to become operational in couple of years..

Power Arrangements for Delhi Commonwealth Games

commonwealth games power arrangement

Capacity building on the electricity front is a priority concern for Delhi government. The government intends to spend over Rs.45 billion on energy during 2007-2012, while over Rs.6.15 billion would be spent in the new financial year.
Present demand for power is around 4,000 MW which will be go around an estimated amount of 5,200 MW in the next two years .
The process of capacity building is under way at full throttle and we hope that the city will have surplus power supply in two years.
Before the beginning of the Commonwealth Games in 2010 energy hungry Delhi will see the availability of power enhanced to 7,000 MW.
The city's peak hour demand is unlikely to cross the 6,000 MW mark in the near future. So around 7,000 MW power capacity puts us in a very comfortable zone.